IDA Advance Office Building, Sligo
Brief Project Description
The IDA Advanced Building in Finisklin Sligo Consisted of 48,000 sq. ft. Shell & Core New Build of 3 Levels for a future category A Office Fit Out. Tim Kelly Group carried out the Full M&E Installation and used Key Co-Ordination tools such as BIM. The project was designed to achieve LEED CS accreditation.
Project Details
Project Value: €2.5m (Mechanical & Electrical Services)
Brief Description of Works
Mechanical Works Consisted of the following works:
- Lead Co-Ordinator Using 3D BIM Modelling.
- Gas Pipework Installation.
- Gas Boilers Including Flue System.
- Solar Panel System For Chlorifier.
- Domestic Water Services.
- Soils & Wastes.
- Supply & Installation Of Sanitaryware.
- LPHW Pipework.
- CHW Pipework.
- Supply & Installation Of Fan Coil Units.
- Supply & Installation Of LPHW Heat Pump & CHW Heat Pump.
- Ventilation Services Including Ductwork, Grilles, VCD’s & FSD’s.
- Supply & Installation Of 2 No. AHU’s Office Areas & 2 no. AHU’s Toilet Areas.
- Supply & Installation Of Full BMS System.
- Testing & Commissioning.
Electrical Installation Consisted of the following works:
- Cable Containment LV Trunking, ELV Cable Tray, FA Cable Tray & LV Cable Tray.
- Sub Mains Cabling.
- Main Distribution Board & 8 No. Sub Distribution Boards.
- Power Factor Correction Unit.
- General Services & Power.
- Lighting & Emergency Lighting.
- DALI Lighting Control System.
- Solar PV System.
- Fire Alarm System.
- Disabled Refuge System.
- Mechanical Wiring.
- Lighting Protection System.
- External Lighting.
- Intruder Alarm System.
- Earthing & Bonding.
- Testing & Commissioning.